Projects
Current & Recent Projects
Project Description | Date | Discipline | Value | Client |
|
|
|
|
|
ANGLO PLATINUM |
|
|
|
|
Electrical and Instrumentation Supply, Installation and Commisioning at Waterval Smelter, SCF1 | 2020 – Current | EC&I | R55 mil | Anglo / GLPS |
Fabrication, Supply and Installation of SMPP Work at Waterval Smelter, SCF1 | 2020 – 2021 | SMPP | R134 mil | Anglo / GLPS |
Refractory Installation at Waterval Smelter, SCF1 | 2022 – Current | Building | R14 mil | Anglo / GLPS |
Gas Cleaning Plant Demolition and Installation | 2021 – 2022 | SMPP | R65 mil | Anglo / GLPS |
Fabrication, Supply and Installation of SMPP Balance Work at Waterval Smelter, SCF1 | 2022 – Current | SMPP | R180 mil | Anglo / GLPS |
Earthworks, Civils and Building Works at Waterval Smelter, SCF1 | 2020 – 2021 | Building | R18 mil | Anglo / GLPS |
Access Gate Civil Works at Waterval Smelter, SCF1 | 2022 – Current | Building | R 3 mil | Anglo / GLPS |
Various supply packages at Waterval Smelter, SCF1 | 2020 – Current | Multi Discipline | Confidential | Anglo / GLPS |
|
|
|
|
|
ARM – Black Rock |
|
|
|
|
Construction of the Proposed New Clinic, RFA Centre and Interview Facilities | 2019 – 2020 | Building | R40 mil | Assmang (Pty) Ltd |
Upgrading of the Existing Administration Building and Construction of New HR, Payroll, SED & Central Filing Offices |
2020 – 2022 | Alterations & Building |
R48 mil |
Assmang (Pty) Ltd |
BR3 Main Security Traffic Flow and Parking | 2021 – 2022 | Civils | R6 mil | Assmang (Pty) Ltd |
Alterations and Additions to Project Offices | 2021 – 2022 | Alterations | R2 mil | Assmang (Pty) Ltd |
Rehabilitation Works for Black Rock Mine | 2021 – 2023 | Rehabilitation | R30 mil | Assmang (Pty) Ltd |
Gamagara Connection Pipeline at Gloria Shaft | 2021 – 2022 | Civils & Piping | R2 mil | Assmang (Pty) Ltd |
Offices and Female Change House at Nchwaning III | 2019 – 2020 | Building | R12 mil | Assmang (Pty) Ltd |
Construction of Underground Charging Bays, Mini-Sub Bays, Office and Tea Room at Nchwaning III | 2021 – 2022 | Civils & Building | R9 mil | Assmang (Pty) Ltd |
Entrance Upgrade, New Lamp Room, Change House & Offices at Nchwaning II | 2022 – 2024 | Building | R125 mil | Assmang (Pty) Ltd |
|
|
|
|
|
ARM – Two Rivers |
|
|
|
|
Pipeline Systems Servitude | 2019 – Current | Multi Discipline | Confidential | ARM |
Tailing Storage Facility | 2018 – Current | Multi Discipline | Confidential | ARM |
Merensky Mine Project – Bulk Earthworks | 2021 – Current | Earthworks | Confidential | ARM |
Merensky Mine Project – Civil Works | 2021 – Current | Civils | Confidential | ARM |
Merensky Mine Project – SMPP | 2021 – Current | SMPP | Confidential | ARM |
Merensky Mine Project – Building Works and Workshops | 2021 – Current | Buildings | Confidential | ARM |
Merensky Mine Project – Electrical Control and Instrumentation incl. OHL | 2021 – Current | EC&I | Confidential | ARM |
Merensky Mine Project – Underground Mining Development | 2021 – Current | Mining | Confidential | ARM |
|
|
|
|
|
ARNOT OPCO |
|
|
|
|
Underground Resuscitation Project | 2020 – 2021 | Multi Discipline | R60 mil | Arnot OpCo |
| BOOST CONSTRUCTION | |||
| Goldreich Street Residential Development Project | 2019 | Building Works | Confidential |
| Kaptein Corner Apartment Building Audit | 2019 | Building Works | Confidential |
| SCATEC SOLAR | |||
| Upper Egypt Solar Plant Project | 2019 | Multi Discipline | Confidential |
| Malaysia Redsol Solar Plant Project | 2019 | Multi Discipline | Confidential |
| Mocuba Solar Plant Project | 2018 | Multi Discipline | R150mil |
| TWO RIVERS | |||
| Tailings Storage Facility | 2018 | Multi Discipline | Confidential |
| GEOTAIL | |||
| BRMO Nchwaning New Slimes Dam | 2018 | Earthworks, Civils and Piping | Confidential |
Previous experience gained through other companies
| BEKKER ARCHITECTS | |||
| New Residential Development Feasibility Study | 2017 | Building Work | R47mil |
| BIGEN AFRICA | |||
| Raising of Clan William Dam Wall – Pre Contract | 2016 | Multi Discipline | Confidential |
| HATCH | |||
| Sasol FAD 6 Project | 2016 – 2017 | Multi Discipline | Confidential |
| Transnet 16Mtpa Rail Phase 1 | 2015 – 2016 | Multi Discipline | Confidential |
| Sasol C3 Expansion Project | 2015 – 2016 | Multi Discipline | Confidential |
| RBM Zulti South Project – Feasibility Study | 2015 | Multi Discipline | Confidential |
| ANGLO AMERICAN COAL SOUTH AFRICA | |||
| New Largo Interim Conveyors Project – Feasibility Study | 2014 | Multi Discipline | Confidential |
| EWRP – Dam Re-lining Project | 2014 | Earthworks, Civils | R7.9mil |
| RLT Refurbishment Project – Implementation | 2013 – 2016 | Multi Discipline | R300m |
| Elders Pre-feasibility Study | 2013 | Multi Discipline | Confidential |
| Project Alexander – Concept Study | 2013 | Multi Discipline | Confidential |
| Zondagsfontein – Main civil works Contract | 2009 | Multi Disciplinary | R86.9mil |
| Phola Coal – Main civil works Contract | 2009 | Multi Disciplinary | R203.9mil |
| AURECON | |||
| Middelburg Water Reclamation Plant | 2013 | Earthworks, Civils | R12mil |
| COAL OF AFRICA | |||
| Makhado Project – Feasibility Study | 2011 – 2013 | Multi Discipline | R4bn |
| Greater Soutpansberg Project – Concept Study | 2012 – 2013 | Multi Discipline | Confidential |
| TWP | |||
| Lehating Manganese Mine – Bankable Feasibility Study | 2012 | Multi Discipline | R1.3bn |
| Seawall – BFS Review | 2012 | Multi Discipline | Confidential |
| MATOMO PROJECTS | |||
| Evander Tailings Re-treatment Project – Implementation | 2014 | Multi Discipline | Confidential |
| Bramber Tailings Re-treatment – Feasibility Study | 2012 | Multi Discipline | Confidential |
| KUMBA IRON ORE THABAZIMBI MINE | |||
| Phase 2 Remedial – Implementation | 2010-2015 | Structural Steel and Corrosion Protection | R140m |
| Structural Steel Remedial Work – Feasibility | 2009 | Structural Steel and Corrosion Protection | R27m |
| Total Fire Water Upgrade Project | 2013 – 2014 | Civils, Piping | R3mil |
| KUDUMANE MANGANESE RESOURCES | |||
| KMR Mine Capital Infrastructure Audit | 2014 | Multi Discipline | Confidential |
| SEDGMAN | |||
| XCSA Atcom East – CHPP Plant Upgrade – Implementation | 2010 | Civils, Structural Steel, Mechanical and Piping, E&I, Substation Buildings | R450m |
| Benga New CHPP Plant – Implementation | 2010 | Civils, Structural Steel, Mechanical and Piping, E&I, Buildings | R850m |
| 35 Ml Concrete Reservoir – implementation | 2009 | Civils | R32m |
| VERGENOEG MINE | |||
| New Tailings Storage Facility | 2010 | Earthworks, Civils and Piping | R13m |
| NKOMATI MINE | |||
| Nkomati Dumps & Co – Disposal | 2009 | Earthworks and Civils | R350m |
| ANGLO PLATINUM RUSTENBURG PMR | |||
| Truck Airlock | 2009 | Building and Structural Steel | R9m |
| KRIEL COLLIERY | |||
| NW Shaft Block R Underground Development – Pre Construction | 2009 | Earthworks and Civils | R51m |
| Block 7 Underground Access New Temporary & Permanent Fans – Implementation | 2009 | Mechanical | R24m |
| Pit 5 Infrastructure Civils – Implementation | 2008 | Civils | R11m |
| Pit 5 E&I Installation | 2008 | Electrical and Instrumentation | R1,7m |
| Block 7 Underground Access – Feasibility Study | 2008 | Earthworks, Civils, Mechanical and Piping, Electrical and Instrumen-tation | R850m |
| Block F Pre-Feasibility Study | 2008 | Earthworks, Civils, Mechanical and Piping, Electrical and Instrumen-tation | R1.8b |
| Block 7 Underground Access Highwall Stabilization – Pre Construction | 2008 | Civils | R8m |
| SACE KROMDRAAI | |||
| Water Reclamation Pre-Feasibility Study | 2009 | Earthworks, Civils, Mechanical and Piping, Electrical and Instrumen-tation | Confidential |
| GOLDER ASSOCIATES | |||
| Tarkwa TSF | 2012 | Earthworks, Civils, Mechanical and Piping | Confidential |
| Mogale Alloys SW Management | 2012 | Earthworks, Civils, Mechanical and Piping | Confidential |
| Finsch FRD Implementation | 2007 | Earthworks, Mechanical and Piping, Electrical and Instrumentation | R117m |
| KAO Diamond Mine – New Tailings Dam | 2007 | Earthworks | R33m |
| Nkomati Pre-Construction and Construction Phase | 2007 | Earthworks, Mechanical and Piping, Electrical and Instrumentation | R244m |
| Harmony Gold Re-Mining and Mega Tailing Facility Feasibility | 2007 | Earthworks, Mechanical and Piping, Electrical and Instrumentation | R4b |
| Golder Moatize Coal FRD Infrastructure | 2007 | Earthworks | R150m |
| De Beers CTP DFS | 2008 | Earthworks, Civils, Mechanical and Piping | R100m |
| WUC Water Reclamation OOM Study | 2008 | Earthworks, Civils, Mechanical and Piping, Electrical and Instrumen-tation | Confidential |
| Black Mountain New Tailings Storage Facility Pre-Construction | 2008 | Earthworks, Civils, Mechanical and Piping | R22m |
| WUC Water Reclamation DFS Study | 2009 | Earthworks, Civils, Mechanical and Piping, Electrical and Instrumen-tation | Confidential |
| Rand Uranium New Tailings Storage Facility DFS Study | 2009 | Earthworks, Civils, Mechanical and Piping | R45m |
| THUTHUKA | |||
| Boynton Platinum Pipeline Project – Implementation | 2008 | Mechanical & Piping | R53m |
| UNION MINE | |||
| Rehabilitation of Old Opencast Areas | 2007 | Earthworks | R12m |
| SACE WATER RECLAMATION PLANT | |||
| 25Ml/day Water Treatment Plant Implementation | 2007 | Earthworks, Civils, Mechanical and Piping, Electrical and Instrumen-tation | R181m |
| Potable Water Pipeline to Witbank Municipality | 2007 | Mechanical and Piping | R12m |
| Construction of 2 x 10Ml Concrete Reservoirs | 2007 | Civils | R13m |
| Small Works Implementation | 2007 | Civils | R11m |
| Phase 2: 8Ml/day Water Treatment Plant Implementation | 2007 | Earthworks, Civils, Mechanical and Piping, Electrical and Instrumen-tation | R60m |
| Water Distribution Network Feasibility Study | 2007 | Mechanical and Piping | R50m |